Accessibility in Himachal Pradesh

Ramp gradients, lift car sizes, door widths and accessible sanitation — the Harmonised Guidelines as they apply here.

What must be barrier-free?

Ramp slope ≤1:12, individual runs ≤9.0 m with 1.5 m landings, width ≥1.5 m, handrails at 760 & 900 mm both sides, non-slip finish.

CPWD Harmonised Guidelines §5 — verify — and 5 related rules below.

The rules — all 6

Barrier-free entrance ramp

verify

Ramp slope ≤1:12, individual runs ≤9.0 m with 1.5 m landings, width ≥1.5 m, handrails at 760 & 900 mm both sides, non-slip finish.

CPWD Harmonised Guidelines §5 — verify · Appendix-7 (projects over 2,500 m²) · Appendix-1 (general buildings)
Slope ratio 12
Max run m 9
Landing m 1.5
Width m 1.5

Accessible lift car

verify

Where a lift is required, at least one car ≥1.1 × 2.0 m (13 passenger) with 0.9 m clear door, Braille buttons at 0.9–1.2 m, audio announcement.

CPWD Harmonised Guidelines §6.4 — verify · Appendix-7 (projects over 2,500 m²)
Car w m 1.1
Car d m 2
Door m 0.9

Doors & wheelchair circulation

verify

Clear door width ≥0.9 m on accessible routes; 1.5 m Ø wheelchair turning circles at lobbies and corridor ends; corridor ≥1.5 m on accessible routes; tactile guiding paths at entrances.

CPWD Harmonised Guidelines §6.1 — verify · Appendix-7 (projects over 2,500 m²) · Appendix-1 (general buildings)
Door m 0.9
Turning m 1.5

Accessible parking bays

verify

1 accessible bay per 25 car spaces (min 1), 3.6 m wide, nearest to the accessible entrance, signed.

CPWD Harmonised Guidelines §4.2 — verify · Appendix-7 (projects over 2,500 m²)
Per cars 25
Bay w m 3.6

Accessible toilet

verify

Public/commercial areas: at least one wheelchair-accessible WC 2.2 × 2.25 m with grab bars and outward/sliding door.

CPWD Harmonised Guidelines §6.9 — verify · Appendix-7 (projects over 2,500 m²)
W m 2.2
D m 2.25

Lift

verbatim

Lift mandatory for more than 4 storeys + 1 parking floor, with promoter-funded power backup for lift and lighting.

Appendix-7 (2022) Reg 16(iii) · Appendix-7 (projects over 2,500 m²)
Storeys 4
5 of these 6 were encoded from secondary sources rather than read off the gazetted text — they carry a “verify” tag above. The engine applies them and the substance is believed correct, but confirm the exact figure against the notification before you build to it.
Worked example — a 500 m² plot on a 9 m road

Computed live by the same engine that produces the drawings — not a stored example.

9 m road 2 m rear 3 m front 2 2 319 m²

Drawn square for clarity. A real tatima is not square — that is what the tracer is for.

RegimeAppendix-1 (General Building)
FAR1.75
Setbacks (F / R / sides) 3 / 2 / 2 m
Buildable footprint319 m²
Height cap21 m
Storeys3
Permissible built-up 875 m²
Parking required9 ECS

500 m² × FAR 1.75 = 875 m² permitted. The 319 m² footprint over 3 storeys could hold 956 m², so FAR is the binding constraint — the height allowance is not fully usable here.

Sources on this page
  • CPWD Harmonised Guidelines §5 — verify
  • CPWD Harmonised Guidelines §6.4 — verify
  • CPWD Harmonised Guidelines §6.1 — verify
  • CPWD Harmonised Guidelines §4.2 — verify
  • CPWD Harmonised Guidelines §6.9 — verify
  • Appendix-7 (2022) Reg 16(iii)

Official text: HP Town and Country Planning Rules, 2014 ↗

Spotted something wrong?

Rules change and we would rather hear it from you than have somebody build to a stale number. No account needed.

Does your plot comply?

Trace your tatima and these 6 rules — and the 74 others — are checked against your actual boundary, with the number behind each verdict.

Check my plot → All Himachal Pradesh rules →
Ask AI

Nothing matched in the rulebook — try other words (parking, height, fire, setback, water…).

looking it up…

Answers come straight from the building rules for 12 states we cover, plus the glossary and calculators — each with its citation.